Creating Factory Calender for Plants in SAP using "SCAL"

Factory Calender

A factory calendar distinguishes between working days and non-working days.
Factory calendar contain company specific dates such as alternate working Saturdays, Plant shutdown, weekends, public holidays etc.

TCODE=SCAL, OY05
Menupath=SPRO->IMG->TIME MANAGEMENT->WORK SCHEDULE->DEFINE PUBLIC HOLIDAY CLASSES.

Step 1: Define Public Holidays
Execute TCODE SCAL.

Choose option for creating holiday. than enter details for holiday.


Step 2: Define Holiday Calendar and assign public holidays to holiday calendar.

 Enter Name of the calender and validity than click on button named Assign pub holidays.



Now tick mark the holidays you want to allow


 Step 3: Define Factory Calendar, select the working days and assign holiday calendar to factory calendar. 

Select holiday calender and edit this for working days of a factory.


Above is the standard calender of Germany in SAP System.

Finally Save the data.